France has published an order dated 20 November 2026 governing authorisations for studies and research involving explosive products. The measure appeared in the Official Journal on 22 November 2026 and concerns products outside the separate rules for war materiel, weapons and ammunition.

Individuals and organisations seeking authorisation under Defence Code Article R. 2352-122 must apply to the Interior Ministry’s central weapons and explosives service, SCAE.

Applications Before Research Begins

Under Article 2, applications must be submitted electronically at least four months before the planned start of the studies or research. SCAE obtains the opinion of the Defence Ministry’s armaments inspector for powders and explosives.

The dossier must identify the fixed or mobile installation, the applicant and all research participants. A technical memorandum must describe the project’s setting, objectives and duration, the materials involved and their origin, the equipment used and the intended disposal arrangements.

Duration And Participants

Article 4 provides for a joint authorisation by the ministers responsible for the interior and defence. It lasts for the duration of the research, subject to a three-year maximum, and specifies safety and security conditions.

Only people named in the authorisation may participate. If the participant list changes, an update must be requested without delay.

Renewals And Earlier Rules

Renewal applications must be submitted at least four months before expiry. The order also provides for suspension or withdrawal in specified safety, security and public-order circumstances.

Article 7 repeals the order of 11 April 1975 on studies and research involving powders and explosives.

Questions about this change

When Must An Application For Explosives Research In France Be Submitted?

The 20 November 2026 order requires an electronic application to SCAE at least four months before the planned research start. It concerns explosive products outside the separate war-materiel, weapons and ammunition rules.

How Long Can A French Explosives-Research Authorisation Last?

The joint ministerial authorisation lasts for the duration of the studies or research, up to three years. Renewal must be requested at least four months before expiry, and participants must be named in the authorisation.

Find out what this means for your products

Foresight follows changes like this one and shows where they reach your substances, products and markets.

Join 3,500+ professionals staying ahead

Foresight Weekly brings the week's regulatory changes across chemicals, product safety, sustainability, ESG and EHS into one email.

Free. Unsubscribe at any time.

Read by professionals at

  • Boeing
  • AstraZeneca
  • Siemens
  • PepsiCo
  • SpaceX