EPA Secures Settlements For Lower Neponset PCB Cleanup Design

EPA has reached settlements covering cleanup design and dam removal at Massachusetts’s Lower Neponset River site. A 54-party agreement covers design, with implementation still under negotiation.

Foresight

2 min readAI-drafted, expert reviewed

An ageing low concrete weir across a river with autumn trees

The US Environmental Protection Agency has reached settlements covering cleanup design and dam removal at the Lower Neponset River Superfund site in Boston and Milton, Massachusetts. The agency announced the agreements on 18 November 2026.

A settlement with 54 parties requires completion of the design for a non-time-critical removal action. A separate agreement with Massachusetts covers both design and implementation of the removal of the Tileston and Hollingsworth Dam.

Design Agreement Covers The Upstream Reach

The 54 settling parties include owners and operators, waste generators and transporters identified as contributors to contamination at the site. Their agreement is an Administrative Settlement Agreement and Order on Consent.

EPA says negotiations will continue over implementation of the removal action. The design settlement therefore does not establish that the group has agreed to carry out the full cleanup.

The planned action covers contaminated sediment and floodplain soil in the most upstream one-mile reach of the 3.7-mile site. EPA identifies polychlorinated biphenyls, or PCBs, and other contaminants of potential concern in that area.

Separate Agreement For Dam Removal

Massachusetts’s Department of Conservation and Recreation owns the Tileston and Hollingsworth Dam. Located at the downstream end of the first-phase reach, the dam impounds contaminated sediment and has been assessed as being in poor condition.

The state settlement covers its removal, which EPA describes as a critical component of the wider action.

Earlier Cleanup Decision And Estimated Cost

EPA issued the action memorandum for this removal work on 5 November 2025. The agency estimates the removal action will cost approximately $78.6 million. That figure is the estimated cost of the action, not a fine or a stated cash settlement.

Questions about this change

Have the 54 settling parties agreed to carry out the full Lower Neponset River cleanup?

The announced agreement covers completion of the removal design. EPA says negotiations over implementation will continue. A separate settlement with Massachusetts covers both design and implementation of the Tileston and Hollingsworth Dam’s removal.

Is $78.6 million the value of EPA’s Lower Neponset River settlement?

No. EPA identifies approximately $78.6 million as the estimated cost of the non-time-critical removal action. The announcement does not describe that figure as a fine or a cash settlement.

Find out what this means for your products

Foresight follows changes like this one and shows where they reach your substances, products and markets.

Join 3,500+ professionals staying ahead

Foresight Weekly brings the week's regulatory changes across chemicals, product safety, sustainability, ESG and EHS into one email.

Free. Unsubscribe at any time.

Read by professionals at

  • Boeing
  • AstraZeneca
  • Siemens
  • PepsiCo
  • SpaceX